Dell N4000 Switch Stack Upgrades - 220 Queen St Auckland Datacenter
Scheduled Maintenance Report for AoNet Broadband
Completed
The scheduled maintenance has been completed.
Posted 17 days ago. Sep 08, 2019 - 06:00 NZST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 17 days ago. Sep 08, 2019 - 05:00 NZST
Scheduled
We will upgrading the operating system on our N4000 stack at 220 Queen St Auckland Datacenter from 6.5.3.7 to 6.5.4.4 which is the latest recommended version by our vendor.

Additionally we will be installing Dell 05KFVW QSFP+ Interface cards to the stack to upgrade the connectivity between our 220 QS MX204 router and the switch stack from 10G to 40G.

During the maintenance window expect two outages of up to 15 minutes in duration as the work is completed.
Posted 25 days ago. Aug 30, 2019 - 16:56 NZST
This scheduled maintenance affected: Core Network.